Cherokee Pipeline Replacement

Cherokee Pipeline Replacement

Audubon Field Solutions provided survey, mapping, and right of way services to assist with the replacement of a 10″ pipeline from Glenpool, OK to Mt. Vernon, MO — a total of 272 miles. Our team played an integral role in supporting the Engineering Team during the Front-end loading (FEL) phase to final as-built documentation. Audubon Field Solutions was responsible for the preliminary survey, right-of-way assistance, routing, construction staking, construction alignment sheet preparation, as-built survey, and as-built alignment sheet documentation, as well as providing geographical information system (GIS) data to be loaded into the Pipeline Open Data (PODS) GIS database.

  • 10″ pipeline stretching 272 miles
  • Survey, mapping, and right of way services
  • Front-end loading (FEL) phase to final as-built documentation support